Sanitary Sewer Replacement Project

Print
Press Enter to show all options, press Tab go to next option

Project Notification Sign Up: To sign up for project notifications, please fill out the 'Notify Me' form by clicking here.

 

February 16, 2018 Update:

The Village’s Sanitary Sewer Replacement Project will continue next week with ongoing sanitary sewer, storm sewer and water main installation. Road Closures will begin on Monday, February 19th at 7a.m. along Summit Street between Lincoln Avenue and Russell Street, along Russell Street between Spring Street and Summit Street, along Spring Street between Russell Street and Lincoln Avenue, and along Lincoln Avenue between Spring Street and Summit Street. Please reference the attached map for these closure locations as well as adjacent streets which will be open to local traffic only. Residents directly affected by closure or local traffic only have been notified via hand delivered flyers which contain additional details, driveway access and parking information.  

All of the North Commuter Parking Lot will reopen in time for commuter parking on Monday, February 19th. Beginning Monday, February 19th North Commuter Lot Parking Permits will be valid only within the North Commuter Parking Lot. All temporary North Commuter Permit Parking locations on the south side of the tracks will be removed and will no longer be valid.

Due to this construction, a section of the South Commuter Parking Lot remains closed to accommodate necessary equipment, staging, and work to be done in the coming months. The Village has secured additional temporary parking spots which will be available by permit only. For more information, please visit www.barrington-il.gov/parking.

Signed pedestrian detours are in place to route pedestrians around the construction site. For your safety, please utilize the signed route.

Any updates to closure timelines and impending closure movements will be provided.  All work is weather dependent and the timeline and progression may be altered as necessary.

If you should have any questions please contact the Sanitary Sewer Replacement Project Hotline at 847-620-4650 or ssrp@barrington-il.gov.

 
The following exhibits are available for viewing online.

  1. Sanitary Sewer Replacement Project – Project Limits Exhibit
  2. Sanitary Service Line Relocation Exhibit
  3. Water Service Line Relocation Exhibit
  4. Infrastructure Improvements Since 2010
  5. South Commuter Parking Lot Temporary Parking Location Map

As new project updates are posted, prior project updates are relocated to the Sanitary Sewer Replacement Project archive.