June 15, 2017 Update:

The Sanitary Sewer Replacement Project construction will continue next week with paving along Liberty and North Avenue. Starting June 19th for a period of approximately 2 weeks, Liberty between Hough and North Avenue will be closed due to concrete curb curing times and associated pavement work. Notification has been provided to residents with affected driveways throughout this street closure. Throughout the paving process, the contractor will make every effort to maintain access through intersections along this stretch. One intersection at a time may be closed during the day, but should reopen each night. The contractor will place a barricade at your driveway during this curb curing process. Only once this barricade is removed may you consider your driveway access restored.

Additionally, the intersection at North Avenue and June Terrace has been closed for the purposes of public safety adjacent to an auger and jack pit from which the Contractor will push pipe underground, south along North Avenue towards Main Street. This intersection will remain closed for the full 5 week work duration, and may remain closed in conjunction with the Main Street Closure which is scheduled from July 10th through August 1st, 2017. As the Main Street Closure approaches, more information on detour routes and overnight work will be provided.

NICOR continues to work on relocations in anticipation of this project. NICOR relocations are currently impacting a significant section of Main Street between Hough Street and Northwest Highway.  Pedestrians may want to consider alternate routes in this area.

Any updates to closure timelines and impending closure movements will be provided via email.  All work is weather dependent and the timeline and progression may be altered as necessary.

If you should have any questions please contact the Sanitary Sewer Replacement Project Hotline at 847-620-4650 or ssrp@barrington-il.gov.

 

*Main Street Customer Parking*

The Village has worked in partnership with AT&T to offer additional public parking spaces in the AT&T lot at 430 E. Main Street.  The two rows located on the west side of the AT&T lot have been signed as 3-hour shopper parking until 5:00pm. After 5:00 pm, there is no three-hour limit,.  No parking is permitted overnight (2am-5am).

 

The following exhibits are available for viewing online.

  1. Sanitary Sewer Replacement Project – Project Limits Exhibit
  2. Sanitary Service Line Relocation Exhibit
  3. Water Service Line Relocation Exhibit
  4. Temporary Parking Areas and Road Closure Map
  5. Infrastructure Improvements Since 2010