Development & Construction Updates

Stay informed about the latest developments, construction projects and new restaurant and retail businesses in Barrington! Check back regularly to learn about ongoing infrastructure improvements and upcoming projects that continue to shape the future of our Village.

Construction Updates

Main Street Pedestrian Bridge Replacement Project

The pedestrian bridges over Flint Creek on the north and south sides of East Main Street will be replaced soon. A section of sidewalk on both the north and south sides of Main Street will be closed for several weeks to accommodate this work. During this time, please use caution and follow the detour route. Click HERE for a map of the closure and detour route.

Project Status: Sidewalk closure and project staging beginning Friday 11/6/2026.

Downtown Streetscape Enhancement Project

Phase I of the downtown streetscape enhancement project is complete! The scope of work included the removal of pavers, installation of new sidewalks and clay brick accents, relocation of the trash enclosure on Station Street, expanded outdoor dining areas and enhanced landscaping throughout Cook Street, Station Street and the northwest segment of Park Avenue.  Stayed tuned for more information on Phase II! 

2026 Village of barrington Road Improvements

The 2026 Village of Barrington road improvements were completed on the following streets:

  • Applebee Street
  • Fairfield Drive
  • Chateau Bourne
  • South Grove Avenue (resurfacing between Illinois Avenue to southern Village limits)
  • South Cook Street in Village Center
  • East Station Street in Village Center
  • APatching work throughout the Village

Project Status: Complete!

Park Avenue Plaza Project

The Village is focused on expanding outdoor areas, beautifying the downtown and providing additional opportunity for outdoor dining. We are finalizing construction design plans for a brand-new community gathering space on Park Ave. This project will convert a small section of roadway into a outdoor plaza space that can accommodate outdoor gatherings, provide adjacent businesses with outdoor patio and dining space, and continue to drive positive investment in our downtown.

Project Status: Construction is anticipated to begin in fall 2026/spring 2027.

U.S. Route 14 Grade Separation (Underpass) Project

The public is encouraged to stay informed throughout the project by visiting the dedicated project website at www.us14underpass.com and signing up for email updates. Fully funded and supported by multiple agencies, this initiative promises transformative changes to the area. Additional project renderings are available on the website for a glimpse into the future of Route 14.

Project Status: See the project website for the latest timeline. 

Construction Projects

Barrington High School Auditorium Project

The petitioner is proposing to construct a new auditorium and several classroom expansions and modifications to the existing parking lot. The initial request to rezone the properties along Main Street to expand the parking lot has been removed from the petition and is no longer under consideration.

Project Status: The Village Board approved the project at the Feb. 23, 2026 meeting.  The project is under construction.

Questions? Please contact Village Planner Katie Rivard at krivard@barrington-il.gov or (847) 304-3463.

Townhome Development @ Taylor & 20th Streets

The petitioner originally proposed to annex the subject property into the Village and construct a 21-unit multi-family residential building and related site improvements, including but not limited to, parking, landscaping, sidewalk, etc.  The proposed 21-unit development was recommended for denial by the Plan Commission at the February 17, 2026 public hearing.  The developer elected to put their application on hold while they reconsidered the proposed use of the subject property.  The developer attended the April 14, 2026 Plan Commission meeting to discuss a revised housing concept for a 12-unit townhouse development and associated site improvements.  The developer has elected to move forward through the public hearing process to seek approval of the revised proposal for a 12-unit townhouse development.

Project Status:  The Village Board approved the project on October 26, 2026.  The project is awaiting site development permit submittal. 

Questions? Please contact Jennifer Tennant, Director of Development Services, at jtennant@barrington-il.gov (847) 304-3462.

Claremont

Approval has been granted for the Claremont subdivision at 617 W. Main St., the former PepsiCo site. The development includes 88 custom luxury single-family homes in a gated community with many on-site amenities, including a clubhouse, pool, cabana, sports courts, walking paths and more. The total site is approximately 94 acres; however, development will only occur on the north portion of the site and will not extend past Hidden Lake.

Project Status: Site development work is underway.

Questions? Please contact Village Planner Katie Rivard at krivard@barrington-il.gov or (847) 304-3463.

150 Washington Street

Approval has been granted for the development of an eight (8) unit attached single-family row home building at 150 Washington St., the site of the former BMO Bank drive-thru facility. The proposed project will include a complete demolition and redevelopment of the site, including utilities, parking, lighting and landscaping, etc.

Project Status: Construction is nearing completion!

Mylo Development

Many of you who have been around the Village for a long time will know this site as “Redevelopment Area #1” or the “Golden Triangle” which has identified as part of the Village’s redevelopment considerations as far back as the 1990s. This site has presented challenges for a number of years due to the unique nature of the site being bound in a perfect triangle between the Metra tracks to the south, the CN tracks to the north and Hough Street to the east. The Village is very fortunate that this redevelopment area caught the eye of a local developer, Joe Taylor of Compass Point Development. Construction should begin in late fall on a multi-use building with 125 residential units, over 12,000 square feet of restaurant and retail space, and 37 car condominiums – luxury vehicle storage and personal recreational space at the rear of the site.

Project Status: Construction is scheduled to begin in fall 2026.

Self-Storage Facility

Approval has been granted for the construction of a new approx. 100,000 sq. ft. self-storage facility and related site improvements located at 1195 S. Northwest Hwy.

Project Status: Construction timeline has not been established at this time.

New Restaurant & Retail Businesses

BOCADO & Retoro Omakase - 133 Park Avenue

The Village is excited to share the news that celebrity chef, restaurateur and Barrington-are resident Fabio Viviani is opening his latest restaurant concept, BOCADO, in downtown Barrington this fall!

Located at 133 Park Avenue, BOCADO will center on shareable plates, bold yet approachable flavors and a thoughtfully crafted beverage program, all within a warm, energetic atmosphere designed for everything from weeknight dinner to cocktails and late-night-offerings.

BOCADO is only the first phase of Viviani’s plans for Barrington.  Phase II will introduce a second concept, Retoro Omakase, located downstairs in the same building! 

Project Status: BOCADO opening soon! 

Motor Werks Porsche

Approval has been granted for the construction of a new stand-alone Porsche dealership and related site improvements at 24 E. Dundee Rd., the northwest corner of Grove Ave and Dundee Rd.  

Project Status: A permit for the project has been issued and construction is underway.  

Kurbside Pizza - 215 N. Hough Street

Kurbside Pizza, a popular area food truck, is opening their first brick and mortar location in Barrington! Kurbside Pizza will provide a modern, family-friendly destination serving up New York-style artisan pizzas, paninis, salads and more! Visit their website here or follow them on socials @kurbsidepizza

Project Status: Interior construction is underway!

Taco Maya - 108 S. Northwest Hwy (former Dunkin' space)

Taco Maya, a regional Mexican resturant, will be opening their 12th location in Barrington this summer! Taco Maya is an authentic fast casual Mexican restaurant serving delicious, traditional food freshly made in house. 

Project Status: Interior construction is underway!

Bundle - Shops of Flint Creek

Bundle, a new quick service restaurant, will be opening in the Shops of Flint Creek in summer 2026.  Bundle will specialize in East-Asian dumplings, noodles and bubble tea. 

Project Status: Interior construction is underway!

Bell House Books

Bell House Books is a woman-owned, independent bookstore bringing thoughtfully curated reads and community-centered programming to Barrington. With a focus on readers of all ages, they are creating a welcoming space to discover books, connect, and gather. Their brick-and-mortar location is coming to downtown Barrington in the Ice House Mall in Summer 2026.

Visit the Bell House Books website or follow on IG @bellhousebooks for more information!

Project Status:  Now open!

The Pepper Pot - Ice House Mall

The Pepper Pot is a full service needlepoint shop and lounge opening soon in the Ice House Mall.  The Pepper Pot will sell needlepoint canvas, fibers and accessories.  The lounge will create a social space for needlepoint classes and events as well as mahjong classes, open play and leagues! Check out their website here.

Project Status:  Now open! 

Fix Sandwich Shop - 113 S. Cook Street

Barrington’s newest sandwhich shop, Fix Sandwich Shop, is relocating to 113 S. Cook Street in the heart of downtown!  Fix Sandwich Shop features homemade bread, Italian street sandwiches and wonderful baked goods.  

Project Status: Now open! 

Long Story Short Pub

The space at 113 E. Main St. is currently undergoing renovations to become the new eatery, Long Story Short Pub.

Project Status: Now open!

Dunkin' & Baskin Robbins Drive-Thru

The new Dunkin’ & Baskin Robbins drive-thru facility at 306 W. Northwest Hwy. is now open!

The former facility and 108 S. Northwest Hwy. is now closed and the Village is working with the broker on that site.

Project Status: Now open!

Posh Plants & Curios

Posh Plants and Curios, located at 122 E. Main Street, is a retail plant botique with a focus on plant sales but also selling home goods, upscale decor, candles, rugs, textiles and collectables.

Project Status:  Now open!